Facility Construction

Project Scope

Construct a new building for the district’s program servicing students who qualify for transition services through special education between the ages of 18 and 22. The program currently resides in portable buildings on the Cedar Park HS campus, as well as rented space at the YMCA Twin Lakes facility. This project puts the program in a single facility. 

The new location will be in a lot next to LISD’s Central Transportation and Support Services buildings [map].

This is a combined project location with the Science Materials Center. These two projects will be located on the same lot to further accommodate the work-based learning opportunities available to 18+ Transition Services students at the Science Materials Center.

Project Status

  • August 2024
    At the August 22, 2024 Board Meeting, Trustees approved Guaranteed Maximum Price (GMP) #2 for the Special Education 18+ Transition Services program and the Science Materials Center. GMP #2, in the amount of $32,737,659 is for the start of the construction phase of the project.

    Rezoning passed by the city of Cedar Park.
  • July 2024
    Meeting with the City of Cedar Park for rezoning of the property from residential to public service use. The Planning and Zoning committee already passed and now it goes to the City council for approval. Final approval should happen at the end of July council meeting.
  • May 2024
    At the May 23, 2024 Board Meeting, Trustees approved Guaranteed Maximum Price (GMP) #1 for the Special Education 18+ Transition Services program and the Science Materials Center. GMP #1, in the amount of $554,781 will go toward equipment, services or materials that must be secured well in advance and early project startup needs. Construction is projected to start later this year.
  • March 2024
    At the March 7, 2024 Board Meeting, VLA Architects and the Leander ISD Construction Management team presented updates, including preliminary renderings of the proposed site.
  • The design team is meeting with district representatives to incorporate all needs of the project.
  • August 2023
    At the Aug. 24, 2023 Board meeting, Trustees approved the architect and construction manager.

Project Details

Phase

Pencil Icon

Design ✓

Paperwork icon

Permitting & Bidding

Construction icon

Construction

Setup icon

Setup

Building icon

Move-In

Estimated Timeline

Start: Fall 2023 (Start of Design phase)
Finish: To be determined

Funding Source

Bond 2023

Estimated Project Cost

This project’s budget has been combined with the Science Materials Center project occurring at the same location.

18+ Transition Services: $22,261,930
Science Materials Center: $19,892,625
Total: $42,154,555

Guaranteed Maximum Price (GMP)

Note: The actual cost will be listed here upon project completion. Any money leftover from the budget goes into project savings, managed by the Bond Oversight Committee.

Contractors

  • Architect: VLK Architects
  • Construction: Joeris General Constructors

Related Project