Mechanic Shop Updates
Project Scope
Provide updates to the Plant Services Mechanic Shop located west of the District Administration building [map]. The building is the district’s original transportation facility built in the 1970s. It has never been updated.
Project Status
- August 2024
Civil permits are still pending. Page Turn Review completed at the end of July. Construction is scheduled to start in the fall. - July 2024
Final construction documents to be completed soon. Civil permits are pending. - The design team is meeting with district representatives to incorporate all needs of the program.
- August 2023
At the Aug. 24, 2023 Board meeting, Trustees approved the architect and construction manager.
Project Details
Phase
Estimated Timeline
Start: Fall 2023 (Start of Design phase)
Finish: To be determined
Funding Source
Bond 2023
Estimated Project Budget
$10,842,838
Guaranteed Maximum Price (GMP)
GMP(s) will come later in the process and go before the LISD Board for approval.
Note: The actual cost will be listed here upon project completion. Any money leftover from the budget goes into project savings, managed by the Bond Oversight Committee.
Contractors
- Architect: PBK Architects
- Construction: Bartlett Cocke General Contractors
- Engineer
- Mechanical, Electrical, Plumbing: MEP Engineering
- Structural: Pickett, Kelm & Associates
- Civil: Halff
South Warehouse Facility Additions & Renovations
Project Scope
Renovate and add to the district’s warehouse facility located in the southern portion of the district, adjacent to the Grandview Hills Elementary campus site. [map]
The redesigned support complex will include a location for warehouse storage and a mechanic shop, along with the South Transportation Terminal and Information Technology Services’ second broadband network node.
Project Status
- The design team is meeting with district representatives to incorporate all needs of the program.
- August 2023
At the Aug. 24, 2023 Board meeting, Trustees approved the architect and construction manager.
Project Details
Phase
Estimated Timeline
Start: Fall 2023 (Start of Design phase)
Finish: To be determined
Funding Source
Bond 2023
Estimated Project Budget
This project’s budget has been combined with the South Transportation Terminal and Second Broadband Network Node projects occurring at the same location.
South Transportation Terminal: $20,383,942
Second Broadband Network Node: $7,000,000
South Warehouse Facility Additions & Renovations: $2,798,150
Combined: $30,182,092
Guaranteed Maximum Price (GMP)
GMP(s) will come later in the process and go before the LISD Board for approval.
Note: The actual cost will be listed here upon project completion. Any money leftover from the budget goes into project savings, managed by the Bond Oversight Committee.
Contractors
- Architect: PBK Architects
- Construction: Bartlett Cocke General Contractors
- Engineer
- Mechanical, Electrical, Plumbing: MEP Engineering
- Structural: Pickett, Kelm & Associates
- Civil: AtkinsRéalis
Replacement Vehicles
Project Scope
Replace aging plant services fleet and grounds motorized vehicles that are 8–10 years old or at the end of life.
- Maintenance vans (20)
- Grounds trucks (20)
- Grounds mowers, utility vehicles and tractors
The fleet is reaching end of life and requires more maintenance to keep them running. For example, the current distribution center forklift was acquired in 2009 and needs frequent repairs. Repairs in 2021–22 were more than $15,000.
Project Status
- Working on procurement process for remaining items. The 2023 auto strike has had an impact on orders.
- November 2023
Six (6) Ford F150 single cabs purchased scheduled to be delivered. - October 2023
Purchased and received three (3) vans.
Project Details
Phase
Estimated Timeline
Start: Summer 2023 (Start of Purchasing process)
Finish: Summer 2024
Funding Source
Bond 2023
Estimated Project Budget
$1,928,840
Actual Cost
The actual cost will be listed here upon project completion. Any money leftover from the budget goes into project savings, managed by the Bond Oversight Committee.
Vendor(s)
- Chevrolet
- Ford
- Enterprise