School Construction
Project Scope
Elementary School #30 will be located in the northwest part of the district near Devine Lake Park off of San Gabriel Parkway and Bagdad Road in Leander [map]. The school is scheduled to welcome its first class of students in the 2024–25 school year. When it opens, it will provide enrollment relief to Bagdad and Plain elementary schools.
In the land purchase agreement, Leander ISD has a clause in the contract that the school district will build roads as private drives with the exception of San Gabriel Parkway, a public street. When a landowner develops the surrounding the property, they will not be permitted access to the drives unless they pay 50% of the cost to build the roads, including any soft cost. Once they have paid the cost, the roads will be dedicated to the city and made public streets.
The roads will start during in the early phase of the school’s construction project.
Project Status
- August 2024
Building construction is complete with minor punch items being finalized. The Health Department re-inspection is scheduled for mid-August. Sod has been installed. Site Inspections are ongoing. he civil engineer has submitted the Final Plat to the City of Leander which is the last step to getting Final Certificate of Occupancy.
Admin and Staff moved in late July. Hisle ES opened to students on August 14, 2024. - July 2024
Construction is progressing as scheduled. Furniture is now being moved into Areas A, B and D (Grades 2-5). The final fire inspection is scheduled for mid July. If the inspection passes, Admin will move in late July and furniture will be moved into
area C (K-1). - March 2024
At the March 28 board meeting, Trustees approved the naming committee’s recommendation to name its newest school after long-time Trustee, Donald Lewis Hisle, who served on the LISD Board for 23 years before retiring in 2018. - February 2024
Road/site paving, electrical & plumbing rough-in, framing, and structural steel construction are all currently ongoing projects. Roofing dry-in phase has now been completed in one section. - October 2023
Insulated Tilt-wall Panels and structural steel going up around the school site. - June 2023
Construction underway (including roads). - May 2023
Held Groundbreaking Ceremony - April 2023
At the April 13, 2023 Board meeting, Trustees approved Guaranteed Maximum Price (GMP) #2 for Elementary #30. GMP #2 – in the amount of $34,249,398, for a total GMP of $54,127,626 – is for the construction phase of the project. - November 2022
At the Nov. 10, 2022 Board meeting, Trustees approved Guaranteed Maximum Price (GMP) #1 for Elementary #30. GMP #1, in the amount of $19,878,228, funded long-lead procurement items and early project startup needs. - July 2022
At the July 21, 2022 Board meeting, Trustees approved Bond Oversight Committee’s recommendation to fund the school through bond savings.
Project Details
Phase
Estimated Timeline
Start: June 2023 (Start of Construction phase)
Finish: August 2024
Funding Source
School Construction: Project savings from the 2007 & 2017 bonds
Roads: Bond 2023
Estimated Project Budget
School Construction: $61,120,968
Roads: $14,000,000
Total: $75,120,968
Guaranteed Maximum Price (GMP) *
- GMP #1: $19,878,228
Approved at Nov. 10, 2022 Board Meeting - GMP #2: $34,249,398
Approved at April 13, 2023 Board Meeting - Total GMP: $54,127,626
* GMPs cover construction costs only. The total project cost will incorporate design and permitting fees, along with furniture, fixtures and equipment. Additional GMPs are possible.
Note: The actual cost will be listed here upon project completion. Any money leftover from the budget goes into project savings, managed by the Bond Oversight Committee.
Contractors
- Architect: Pfluger Architects
- Construction: American Constructors
- Engineer
- Mechanical, Electrical, Plumbing: MEP Engineering
- Structural: Pickett, Kelm & Associates
- Civil: AtkinsRéalis